Topic 58 of 76 · Software engineering and digital delivery

Build vs Buy

Build-vs-buy is a structured comparison of custom development against commercial acquisition, on discounted TCO, delivery time, and risk. The empirical priors are one-sided: actual build costs typically exceed projections by 30–40%, bought solutions deploy 40–60% faster, and MIT's 2025 GenAI research found purchased AI tools succeeded ~67% of the time while internal builds succeeded about a third as often.

Why it matters

Health systems face this decision constantly ("make vs commission" in NHS language), and engineering organizations systematically get it wrong in the build direction — because builders estimate the build, not the TCO, and because building is more fun. The economic frame forces the honest comparison: both options priced over the same horizon, both risk-adjusted, and the time difference priced as cost of delay — the term that most often decides the answer and most often gets omitted.

The math

Compare over the same 3–5 year horizon, discounted:

NPV_option = PV(benefits, shifted by time-to-value) − PV(TCO)

Risk adjustments (Green Book "optimism bias" pattern):
  build cost × 1.3–1.4        (overrun prior)
  build time-to-value + 40–60% (deployment delay prior)
  buy: add integration reality-check and exit costs instead

Decision drivers, in the order they usually decide:
  1. differentiation — is this capability your product, or plumbing?
  2. time-to-value × CoD
  3. risk-adjusted TCO

Worked example

A trust needs an e-consent system. Buy: £150k/year SaaS, live in 3 months. Build: estimated £600k + £120k/year maintenance, live in 12 months.

Risk-adjusted build: 600k × 1.35 = £810k; time-to-value ≈ 18 months
5-yr TCO:  buy = 150k × 5 = £750k
           build = 810k + 120k × 5 = £1,410k
Delay term: consent digitization saves £25k/month; build arrives 15 months
            later → CoD = 15 × 25k = £375k

Effective comparison: £750k vs £1,785k — buy wins by ~£1M, and the largest
single term after the build itself is the delay cost nobody had priced.

Build remains right when the capability is differentiating (your product's core algorithm), when no vendor meets a hard constraint (clinical safety, data residency), or when vendor lock-in risk is severe and priced.

Software engineering connection

The transferable health-economics discipline is threefold: prior-based risk adjustment (the 30–40% overrun uplift is the software Green Book optimism bias — apply it mechanically, argue for exceptions rather than from them); comparator honesty (the alternative to building isn't "nothing," it's the best available buy — see opportunity cost); and equivalence testing before cost comparison (if buy and build genuinely meet the same spec, this is cost-minimization analysis and the cheap one wins; if not, the outcome difference must be valued, not asserted).

Pitfalls

  • Comparing vendor list price to un-risk-adjusted build estimates — double flattery toward build.
  • Zero-priced internal labor ("the team's already here").
  • Unpriced lock-in in both directions: vendor exit costs, but also the build's bus-factor and maintenance tenure.
  • Identity-driven builds: "this is core to us" claimed for plumbing — test differentiation against whether customers would notice.